Answered: NEC3 ECC: Is no Time Risk Allowance a reason not to accept the programme?

$
0
0
You would be within your rights not to accept this programme as time risk allowance is a requirement in clause 31.2, and if not complied with a reason to reject under clause 31.3 (doesn't show the information the contract requires. Also could be rejected as "it is not realistic". If TRA is included within the activities the planned Completion will be much more realistic. If they do not need/use the TRA then the planned Completion will start to come forward, which results in terminal float which the Contractor then still owns.