Answered: NEC ECC: what happens if an activity is missed from the Contractors programme.

$
0
0
a. Given that it is an Option A the cost of the fencing is deemed included in the total of the Prices therefore there should be no extra payment (provided it was shown in the Works Information at tender).
b. When the programme is updated under clause 32 the fencing activity should be added.
c. Yes provided that the piling fully complies with the Works Information. The contractor should resubmit his design for acceptance.
d. In accordance with clause 54.2 the Contractor can resubmit the Activity Schedule to realign to the Accepted Programme.  The resubmission should not result in a change to the total of the Prices.