JCT - Client changing specifications - what can I claim?

$
0
0
The contract is a fixed cost jct the client is out sourcing different specifications from the contract i.e. Cheaper bathrooms cheaper floor finishes and external cladding we are still applying ohp to the new specifications but the changes are having a huge impact on the over all contract value. Can I claim the original ohp from the original specifications I understand the Client needs the right to change there mind on specifications