Answered: NEC TSC: Are direct and indirect fees added to all works or only CE?

$
0
0
In answer to your questions :
1) Neither of what you say. As the price is in the Price List, you get paid what is in the Price List - see TSC option A clause 11.2 (17) and (19) with no addition of Fee.

2) I have no idea where you get these percentages from but regardless my answer is the same as in 1.

3) The fee is for compensation events where there is no existing rate - see clauses 63.1 and 63.2.