Under an NEC3 ECC Option C Contract, which has clause 60.1 (19) deleted and replaced with "The works are affected by a Force Majeure Event", is unofficial strike action by the Contractor's operatives and their Subcontractors operatives a Compensation Event?
The operatives who went out on strike have not been paid for the time which they were "out" but the Contractor is seeking a Compensation Event relating to the associated delay.
The operatives who went out on strike have not been paid for the time which they were "out" but the Contractor is seeking a Compensation Event relating to the associated delay.