Contractor is updating the programme but not the Activity Schedule as it's 'too time consuming'. Numerous CE's not on Activity Schedule. As PWDD is Total of Pricea for a completed activity without Defects, presumably the PM cannot include any work against the activities which are not shown on the schedule.
↧