Answered: NEC ECC: Option B, Contract Data part 2 fee percentages

$
0
0
By :
- 'plant' I assume you mean 'Equipment' in NEC speak
- 'materials' = Plant and Materials.
and staff and about are both counted as People

The calculation would be :
Staff + labour = £4,000 x 1.15 (15% percentage for People O/H) = £4,600.
Plant & Materials = £2,000 (there is no percentage)
Equipment = £2,000 x 1.15 (15% percentage for adjustment for listed Equipment) = £2,300
Sub-total = £8,900
Total = £8,900 x 1.15 (15% direct fee percentage) = £9,245