Under an NEC Contract (Option A) a named product (or equivalent) was specified in the Works Information.
According to the Contractor a miscommunication between the manufacturer and the supplier lead to the delivery date being missed and resulted in a delay to the Completion Date of 3 weeks. In order to mitigate this delay, the Contractor proposed an equivalent product but this was not accepted.
Is this a Clause 60.1(19) Compensation Event under?
According to the Contractor a miscommunication between the manufacturer and the supplier lead to the delivery date being missed and resulted in a delay to the Completion Date of 3 weeks. In order to mitigate this delay, the Contractor proposed an equivalent product but this was not accepted.
Is this a Clause 60.1(19) Compensation Event under?