The answer should be b), but it depends on the timings of your Accepted Programme to see how easy this is to demonstrate. If the Contractor was running a week ahead this has created terminal float which is owned by the Contractor. If a compensation event moves planned Completion, then there is an entitlement to move Completion Date by the same amount. This is identified in the clause and guidance notes for 63.3 (or 63.5 in NEC4).
↧