- Our Accepted Programme stated that a licence was to be provided, by the client, at a certain date.
- The works which could only commence once in receipt of the licence were due to start at a later date.
- The licence was issued after the required date shown n the programme but prior to the date shown for the commencement of the activity which required the licence.
- However, we had improved on programme dates resulting in works being stopped whilst we awaited the licence to be issued.
- The client believes there is no merit for a CE here as they provided the licence prior to the programme dates for the activity starting.
- We believe we are entitled to a CE as we lost opportunity to improve on the programme and were delayed on site as a result of the client not providing something by the date shown on the Accepted Programme 60.1(3) .
- The works which could only commence once in receipt of the licence were due to start at a later date.
- The licence was issued after the required date shown n the programme but prior to the date shown for the commencement of the activity which required the licence.
- However, we had improved on programme dates resulting in works being stopped whilst we awaited the licence to be issued.
- The client believes there is no merit for a CE here as they provided the licence prior to the programme dates for the activity starting.
- We believe we are entitled to a CE as we lost opportunity to improve on the programme and were delayed on site as a result of the client not providing something by the date shown on the Accepted Programme 60.1(3) .