NEC ECC: Contractor submitted a programme requesting several weeks beyond Completion Date

$
0
0
Agreed and implementation of 2 CE's resulted in Two weeks delay to completion date but in contractors submission of a revised programme they are now playing further 6 weeks extension of time. This is due to the contractors lack of progress on-site and realistically the time requested seems reasonable to the current progress onsite.

I don't want to accept as this time element was no fault to Client. If accepted them any future CE's that are implemented will start from this date of acceptance.