When the Project Manager assesses the compensation event due to rainfall, do they give only the number of days with rain above the 10 year average or consideration is given to the follow on days where production is greatly reduced due to excessive wet ground conditions?
The project is extensively earthworks and after a rainy day, the following 2 or so days ground conditions are such that little or no production at all is achieved. Is the Contractor not entitled to additional days due to conditions so caused by the rain?