NEC ECC: Can a dispute be declared after the contractual end date?

$
0
0
The contractor was requested by the Project Manager to submit a revised quotation for a compensation event a week and a half before the contractual end date on an Option B contract.

The reply period on the contract is 2 weeks. Would the contractor still be able to refer the matter under Option W1 even after the contractual end date of the contract. The works are not completed yet and no defects certificate have been issued.