NEC ECC: Disallowed costs for standing around time due to a health and safety breach

$
0
0
Enquiring what grounds there are to disallow costs due to a health and safety accident under ECC option C - for Instance if an accident occurs and the site is at a standstill due to investigation. PM instructs the Contractor to cease work due to an investigation, can the Contractor still claim for standing around time, extended prelims or can these be disallowed on any grounds?