I agreed that you should ask for formal confirmation of all the instruction given by the Project Manager and ask for the list of assumptions to be considered for the CE due to the instructed change in design/drawings.
If upon formal receipt of the revised drawings and deviation from the assumptions given by the PM is observed, then you can reassess the CE. This is in accordance with Sub-Clause 61.6.
If upon formal receipt of the revised drawings and deviation from the assumptions given by the PM is observed, then you can reassess the CE. This is in accordance with Sub-Clause 61.6.