Answered: NEC ECC: Can a existing Risk Register item extend contract duration after completion cert issued?

$
0
0
As a compensation event can be notified up to the defects date then the answer is Yes.  It doesn't actually matter whether it is on the Risk Register or not as a CE notification is a separate matter, but be aware of the time bar issue under clause 61.3.