I'm the Contractor on a project, under NEC Option A with a Subcontractor. the Subcontractor has not complied with their method statement and has caused damage to a persons land.
I can't see a CE under 60.1 that is for damage to land, so it would suggest it isn't a CE. The Subcontract doesn't implicitly state that they must comply with their method statement, but the implication is there, as otherwise why write one.
I would like to 'recover' the cost the Contractor is going to have to pay to the landowner however not sure if I can.