Answered: NEC ECS: Subcontractor Programme Alignment

$
0
0
The Subcontractor's programme - and the way they actually work - has to comply with any constraints stated in the Works Information. If sufficient constraints are not stated in the Works Information, then it needs to be changed. That of course is a compensation event.