In the schedule of cost components there are two classifications for People. (1) Directly employed by the Contractor and (2) People who are not directly employed by the Contractor but are paid for by him according to the time they worked while they are at the Working Areas.
Accordingly, WAP shall also be applied for agency supplied staffs if they are working specifically on the project and paid for by the time they worked.