Answered: NEC ECC: Defects Date

$
0
0
The Supervisor is obliged to issue the Defects Certificate either at;

 - the defects date,
   or
 - the end of the last defects correction period, if a later date.

Any outstanding contract administration procedures should not affect the issuing of the certificate, so in response, yes it should still be issued.

Although a compensation event is not notified after the defects date, the matter in question under clause 44 is not a compensation event, as stated under clause 60.1(1).