Answered: JCT - Client changing specifications - what can I claim?

$
0
0
I assume you mean the original OHP as a lump sum. The reality is probably not but in pricing the change as you describe you would be entitled to adjust the OHP percentage if the nature of the work is changing significantly. You may also need to think about an increase in productive supervisory costs (formen etc who would be part of the OHP) depending on the nature of the change.