Subcontract : Option A
We have a subcontractor under an option A Contract. No Start Date but Access Dates.
The Contractor has a 3 week cancellation period to defer these Access Dates written into the Contract Data Part 2.
If the Contractor defers the Access Date by 6 months in line with the 3 week cancellation period; does the subcontractor have grounds to claim prelims for the period of deferment even if they were not ready to start on the original Access Date?