I'm assuming that the preferred subcontractor was identified at tender and has not been introduced as a CE (change in WI).
If that is the case the Contractor is responsible for the performance of the subcontractor including availability. It is unlikely that the circumstances would trigger a prevention CE but that would depend upon the actual circumstances especially the remaining time on the programme.