Answered: NEC ECC: After completion of the whole of the works but before the defects date does the Contractor have to be on stand by to search for or correct Defects?

$
0
0
The relevant clauses in NEC3 are 42.1 "Until the defects date, the supervisor may instruct the contractor to search for a Defect..." and 60.1(10) The supervisor instructs the contractor to search for a Defect and no Defect is found..."

The Supervisor should identify the Defect the contractor is to search for (it can't just be a general request) and the contractor is then obliged to do so.