Clause 30.2 states that the Project Manager decided date of Completion and certifies within one week. However – is it just the paperwork that comes one week later or do they not need to physically take possession of the site back until the issue of that piece of paper one week later?
If the latter, we have some very expensive prelims in terms of security and other costs so should we have allowed for an extra week of that cost within our tender?