NEC ECC: Do you include mitigation within a CE assessment?

$
0
0
We have been awarded a compensation event, which prevented the works from being carried out in sequence and manner that was intended, however in order to keep the works progressing we moved on to another area of works. The guidance notes and the contract all imply that you impact the works at the time of the event to see the effect on the planned Completion. The movement being the entitlement to move Completion Date. During the period of preparing the quote, it is evident that we have managed to mitigate some of the impact, and would seek confirmation if this should be taken in to consideration?