Subcontractor (SC) failed to meet his obligation in terms of providing the works as per agreed programme and clauses 20.1/30.3. despite numerous EW and meetings and communications. SC is under resourced and does not have all the manpower his programme is showing he needs, thus resulting in lack of progress, which will jeopardise meeting a key date. Contractor(C), must meet otherwise C will incur damages (penalties upstream and standing time of other SC's).
I have the same as the previous question in my x18.1 - but this event is a direct result of SC not remedying the situation. or will this be seen as consequential or indirect?
My X18.4 calls for 100% of the total of the prices. What is the C recourse in recovering damages incurred due to SC failure to provide the works? Project Manager does not wish to pull PB nor terminate due to limited duration left to complete the project.
I have the same as the previous question in my x18.1 - but this event is a direct result of SC not remedying the situation. or will this be seen as consequential or indirect?
My X18.4 calls for 100% of the total of the prices. What is the C recourse in recovering damages incurred due to SC failure to provide the works? Project Manager does not wish to pull PB nor terminate due to limited duration left to complete the project.