You should notify the compensation event for lack of access by date stated in CD1. When assessing that compensation event, the effects that will have on the Key Date should be taken into account, which will then agree the value of that event and how much the Key Date should move by. At this stage you should have an assumption from the Project Manager as to when access will be given so you can programme/price accordingly (any further movement could be assessed as a separate CE)
At the moment you should have a "planned Key Date" milestone on your revised programme showing where you currently are, which will be beyond the Kay Date milestone. As and when the CE is implemented, then you can adjust the Prices accordingly but more importantly move the Key Date by the agreed amount.
At the moment you should have a "planned Key Date" milestone on your revised programme showing where you currently are, which will be beyond the Kay Date milestone. As and when the CE is implemented, then you can adjust the Prices accordingly but more importantly move the Key Date by the agreed amount.