Answered: NEC ECC: X7 Delay Costs inserted at £0 per day, Employer trying to counter charge additional PM costs to Contractor

$
0
0
I will keep this brief...

No.

They have no other recourse - that is the whole point of putting them in at zero - to show the Contractor they have no liability and therefore would no doubt have given a cheaper tender price accordingly!

Had they not have included X7 at all, then they could have claimed for losses incurred in a court of law but outside of the contract. By setting X7 at zero they cut of that legal right.