Answered: NEC3 ECC: Option B SSoCC Payments for Electricity

$
0
0
The opening sentence of Equipment 2 states "The following components of the cost of Equipment which is used within the Working Areas (including the cost of accommodation, but excluding Equipment cost covered by the percentage for people overheads).", so in the percentage for people overheads.