hello LA1. My view is that 60.1(19) is not satisfied for a few reasons. The snow did not "stop" "completion" of works. It just stopped the C from working for X days (i.e. Provide the Works). In addition, it is "one of the other CE stated in this contract" - so the CEN fails on that as well since all 3 bullets have to be satisfied (see use of "and" in between each one). As to cl 60.1.(13), it is likely that the snow was not significant enough. A red Police warning could be used to support an argument for event 19 but not for 13. Event 13 requires comparison of data - a relatively easy exercise to do. (Glenn Hide posted a LinkedIn piece on this, which I commented on as well - may be helpful to read this too).
↧