Assuming you are talking about critical path works here it sounds as though your planned Completion was one week ahead of Completion Date. If this compensation event now delays planned Completion by one week, then there is an entitlement to move Completion Date by one week as well (see clause 63.3 under NEC3). This is called terminal float and is owned by the Contractor, and hence retained in the assessments of compensation events.
↧