NEC ECC: Contractor sent to site without an accepted programme

$
0
0
We were a Contractor on a project and we submitted a Clause 31 programme after contract signature.  The Project Manager did not accept the programme.  The contract had one access date for the whole of the works. The date for access passed, as the Employer was not ready to give access.  The Project Manager then insisted we start work on site to construct accommodation works without an accepted programme.  We objected but eventually agreed.  What is the contractual position on programme here?