Answered: NEC ECC: Additional charges over and above X7 Delay Damages

$
0
0
By selecting Option X7 the Employer has liquidated his potential losses into a fixed amount per day in the contract. These damages are an exhaustive remedy for delay in completion of the works and when X7 is selected the Employer cannot also recover any other losses incurred or choose to recover his other losses instead of the amount stated under X7.