Answered: NEC ECC: New Works Information issued with out PMI's

$
0
0
Provided the communication complies with the requirements of clause 13, then it would be a valid instruction. There have been other posts on this subject recently which you can find in a search.

If the instruction changes the Works Information then the Project Manager is also obliged to notify the matter as a compensation event, or, if the PM fails to do so, the Contractor should notify accordingly.