I think the note is irrelevant as it is so vague.
The Contractor should have priced for what was shown on the drawings. The issue of the rationalised construction drawings are a change to the WI which would presumably result in a negative compensation event which reduces the Prices as it is easier to construct.
This assumes that the construction drawings were issued post-contract.
However, if I was a Contractor I would be pointing at clause 63.8 !