Answered: NEC ECC: Change in the WI between tender and construction - what should have been allowed for

$
0
0
I think the note is irrelevant as it is so vague.

The Contractor should have priced for what was shown on the drawings. The issue of the  rationalised construction drawings are a change to the WI which would presumably result in a negative compensation event which reduces the Prices as it is easier to construct.

This assumes that the construction drawings were issued post-contract.

However, if I was a Contractor I would be pointing at clause 63.8 !