Yes there is no mechanism to introduce a new sectional Completion mid contract as you will not have had the chance to assess the risk/cost associated with that within your tender price, and would not be fair if the PM could make their own assessment of this price at this stage. They can instruct the Contractor to try to achieve these new dates, but there will be no delay damage mechanism if these are then missed.
↧