When a resource leaves the project and a new individual is employed is the associated handover period a recoverable cost under an ECC Option E contract? Essentially should the Employer be expected to pay for two people to undertake the same role for a short period of time?
If such cost was included in the Application for payment is there grounds for this to be deemed as Disallowed Cost?
If such cost was included in the Application for payment is there grounds for this to be deemed as Disallowed Cost?