You need to refer to the Method of Measurement that the BoQ was prepared on.
This should be stated in Contract Data Part 1.
The Method will set out how the work needs to be described in the BoQ and what item(s) should be provided for pricing. The item coverage to the item(s) will clarify what the rate should include for (when read in conjunction with the Works Information).
This should be stated in Contract Data Part 1.
The Method will set out how the work needs to be described in the BoQ and what item(s) should be provided for pricing. The item coverage to the item(s) will clarify what the rate should include for (when read in conjunction with the Works Information).