Not ask, but instruct ! (under clause 60.1(1))
You should notify a compensation event at the same time.
The Subcontractor should then give a quotation in accordance with the clause in sub-section 63. A reduction in scope is one of the few compensation events that can result in a negative compensation event for the Prices.
You should notify a compensation event at the same time.
The Subcontractor should then give a quotation in accordance with the clause in sub-section 63. A reduction in scope is one of the few compensation events that can result in a negative compensation event for the Prices.