I'm a Contractor working with my Subcontractor on an Option A ECS. The contract with my client is an ECC Option E.
We have caused our subcontractor delay due to not providing documentation / RAM approval in the time stated in the programme. This has caused works to be pushed back as the subcontractor cannot commence until they have received approval.
The reason for this delay is not the fault of the subcontractor but the Contactor (Long governance processes)
Is the CE for prolongation from the subcontract recoverable by the Contractor to the client ?
We have caused our subcontractor delay due to not providing documentation / RAM approval in the time stated in the programme. This has caused works to be pushed back as the subcontractor cannot commence until they have received approval.
The reason for this delay is not the fault of the subcontractor but the Contactor (Long governance processes)
Is the CE for prolongation from the subcontract recoverable by the Contractor to the client ?