Two obvious things spring to mind to answer this question :
1. How was the original CE worded ? If the original wording is not valid - i.e. it contained the quantities and these were wrong - then it would be another CE under clause 60.1 (1).
2. Does the change in quantities satisfy the criteria listed either in clause 60.4 or 60.5. If 'Yes', it is again a compensation event.