On my current site the client is about to take over the building, our expected completion date is 4 weeks beyond that (due to incomplete external works, internally its complete)
Is take over the right procedure?
Who is responsible for insuring the building during this period?
The supervisor is insisting that during this period they will able do fit out works with direct orders and their own people, it will no longer be "our site" these guys won't have to provide us RAMS or be CSCS etc however they expect us to carry on the insurance cover
Is take over the right procedure?
Who is responsible for insuring the building during this period?
The supervisor is insisting that during this period they will able do fit out works with direct orders and their own people, it will no longer be "our site" these guys won't have to provide us RAMS or be CSCS etc however they expect us to carry on the insurance cover