We’re engaging subcontractors for early contractor involvement. Will the ECS option C with X25 be an appropriate contractual and payment mechanism to complete Stage 1 and proceed to Stage 2 for one of the Subcontractors?
Would the Stage 1 also be susceptible to pain/gain?
Presumably at the time of writing the subcontract the Works Information will only be for Stage 1 (ECI). How do you update the Works Information for the subcontract for continuation into Stage 2?
Would the Stage 1 also be susceptible to pain/gain?
Presumably at the time of writing the subcontract the Works Information will only be for Stage 1 (ECI). How do you update the Works Information for the subcontract for continuation into Stage 2?