Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

Answered: NEC ECC: Weather clause taken out but other CE occurs

$
0
0
No it doesn't warrant another CE - this winter working risk should have been included within the original CE. There is no mechanism to notify a new compensation event.

Your only chance here would be to by agreement get them to see that the original CE did not price that risk and see if they have any sympathy (as they equally did not asses it either) but contractually there is no other remedy for you. It is important that any CE looks at the obvious direct cost but also any wider affects including any additional risk for cost or programme.

Viewing all articles
Browse latest Browse all 3204

Trending Articles