The compensation event quotation should reflect the change in Defined Cost + fee of the event.
The Contractor and Subcontractor can agree to use bill rates to assess the change, in which case the 5 deleted piles would be amended to 0 quantity and an item introduced for the aggregate of the bill value (negative).
If not using Bill rates, the approach I would take is to
establish the BoQ value of the piles which have been deleted.
I would then assess the change in Defined Cost + Fee due to the deletion mindful that materials may already have been delivered etc.
The CV value is the addition of the two; I would note on the CE quotation that the deleted piles would not be included in the PWDD, or would be 0 quantity.
I would then introduce an item in the BoQ for the CE.
The Contractor and Subcontractor can agree to use bill rates to assess the change, in which case the 5 deleted piles would be amended to 0 quantity and an item introduced for the aggregate of the bill value (negative).
If not using Bill rates, the approach I would take is to
establish the BoQ value of the piles which have been deleted.
I would then assess the change in Defined Cost + Fee due to the deletion mindful that materials may already have been delivered etc.
The CV value is the addition of the two; I would note on the CE quotation that the deleted piles would not be included in the PWDD, or would be 0 quantity.
I would then introduce an item in the BoQ for the CE.