Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

NEC ECC: Liability for an uncorrected Defect

$
0
0
I understand the principle behind clause 45 and that the PM "assesses" the cost of correcting a Defect but if the Employer decides to have a third party correct the Defect does this mean that the Contractor will no longer be accountable for that element of the work should a latent defect/issues appear at a later stage?

Obviously, the Contractor's argument will be should a latent defect/issue appear it is not his responsibility or fault and any issue is down to the work carried out by the third party.

Viewing all articles
Browse latest Browse all 3204

Trending Articles