In NEC3 TSC the risk allocation is through compensation events - there are 15 standard compensation events 60.1(1) to (15). In a standard TSC the list of compensation events DOES not include weather or physical conditions (so these are Contractor risks).
The Employer's risk are identified in clause 80.1 and any additional Employer risks are identified in the Contract Data.
The Subcontractor should include for risks which are his under his subcontract. You may have to remind the Subcontractor what he should be including in this quotation for a compensation event.
The Employer's risk are identified in clause 80.1 and any additional Employer risks are identified in the Contract Data.
The Subcontractor should include for risks which are his under his subcontract. You may have to remind the Subcontractor what he should be including in this quotation for a compensation event.