Answered: NEC ECS: Defined cost and Compensation events

$
0
0
If the reason for the TM issues are not the Subcontractors fault and is a reason for being a compensation event then yes the extra day will be assessed in terms of the Defined Cost incurred and the target should raise by the same amount agreed. It would not be fair if through no fault of the Subcontractor this ate into their own gainshare.