The published version of the Schedule and Shorter Schedules of Cost Components only requires rates for categories of employee carrying out design and manufacture and fabrication outside Working Areas, not people per se.
All of the main Options allow rates and lump sums to be used to assess a compensation event but only by agreement between the Contractor and the Subcontractor (e.g. clause 63.14 in Option A).
So the rates you have in Contract Data part two are erroneous, even if it states that they will be used, this contradicts clause 63.14 which leaves you with an ambiguity or inconsistency which can be resolved under clause 17.1. Unfortunately it's likely the Contractor will attempt to resolve it in his favour.
All of the main Options allow rates and lump sums to be used to assess a compensation event but only by agreement between the Contractor and the Subcontractor (e.g. clause 63.14 in Option A).
So the rates you have in Contract Data part two are erroneous, even if it states that they will be used, this contradicts clause 63.14 which leaves you with an ambiguity or inconsistency which can be resolved under clause 17.1. Unfortunately it's likely the Contractor will attempt to resolve it in his favour.